Lucara’s Karowe Diamond Mine Revenue Rises 19% as US$779 Million Underground Project Progresses

Lucara’s Karowe Diamond Mine Revenue Rises 19% as US$779 Million Underground Project Progresses

Botswana’s Karowe Diamond Mine Records US$61.1 Million in Quarterly Sales as Underground Expansion Advances

Lucara Diamond Corp has recorded a 19% year-on-year increase in revenue from its Karowe diamond mine in Botswana, generating US$61.1 million during the third quarter of 2026 as the operation prepares to transition from open-pit to underground mining.

The improved financial performance was supported by the sale of 113,227 carats, including an exceptional 1,303-carat Type IIa diamond recovered in July.

The company recorded adjusted operating earnings of US$32.8 million, while net income reached US$6.6 million. Cash generated from operating activities increased from US$15.1 million to US$35.3 million compared with the corresponding period in 2025.

Following the stronger sales performance, Lucara raised its full-year revenue forecast from US$100–130 million to US$140–160 million.

Karowe Records Strong Operational Performance

Karowe recovered 96,767 carats during the quarter, including 163 diamonds weighing more than 10.8 carats.

Among these were the mine’s tenth diamond exceeding 1,000 carats and eight additional stones weighing more than 100 carats.

Ore processing increased to 829,822 tonnes, compared with 744,753 tonnes during the corresponding period in 2025, while production costs declined from US$25.65 to US$22.41 per tonne processed.

Lucara attributed the improved cost efficiency to increased processing volumes and reduced open-pit mining activity, despite higher electricity costs.

US$779.2 Million Underground Expansion Advances

Open-pit mining at Karowe is scheduled to conclude during the fourth quarter of 2026, with stockpiled ore expected to sustain processing operations during the transition.

The underground development, estimated to cost US$779.2 million, is expected to extend Karowe’s operational life to 2038, with full-scale underground production anticipated in the first half of 2028.

As of 30 September 2026, Lucara estimated that US$245.2 million remained necessary to complete the project, of which US$92.9 million had already been committed.

Third-quarter capital expenditure on the development reached US$40.7 million, covering equipment procurement, shaft infrastructure and underground development.

The company has completed the transition from shaft construction to lateral development, with cumulative underground development reaching 2,121 metres by the end of September.

The production shaft has also been transferred to the operating team, while the necessary mining equipment has arrived on site.

Navigating Global Diamond Market Challenges

Lucara’s operational transition comes amid continued pressure on the global natural diamond industry, driven partly by competition from laboratory-grown diamonds and changing consumer demand.

However, the company has noted signs of improving prices for larger, rarer natural diamonds, supported by limited supply and resilient demand for high-value stones.

Global natural diamond production is projected to fall below 100 million carats in 2026, compared with more than 150 million carats less than a decade ago.

For 2026, Lucara expects diamond recoveries and sales of between 340,000 and 360,000 carats each, alongside ore processing of between 2.8 million and three million tonnes.

The successful completion of Karowe’s underground expansion will be critical to sustaining the mine’s long-term production, financial performance and contribution to Botswana’s diamond industry.

Loading

Share this article

Leave a Reply

Your email address will not be published. Required fields are marked *

You have successfully subscribed to the AMG Weekly newsletter

There was an error while trying to send your request. Please try again.

Angolan Mining Oil & Gas will use the information you provide on this form to be in touch with you and to provide updates and marketing.